The government approved 6 new brownfield urea plants under the National Investment Policy for Urea
DDecode Civils
· 3 min read
NIPU-2026: Six New Urea Plants for Self-Reliance
Why in News
The government approved 6 new brownfield urea plants under the National Investment Policy for Urea (NIPU)-2026. They bring an expected investment of about ₹54,000 crore and aim at self-reliance in urea production.
News Summary
Each plant will have an annual installed capacity of 12.7 lakh metric tonnes (LMT). The six plants are:
MFL-Madras (Chennai, Tamil Nadu), a PSU plant replacing a unit over 60 years old.
NFL Nangal (Punjab), a PSU plant replacing a 50–55 year old unit of 4.73 LMT.
KFL-Shahjahanpur (Uttar Pradesh), a cooperative project of KRIBHCO.
Matix-Panagarh (West Bengal), a private project. It will be the state's second urea plant.
CFCL Gadepan (Kota, Rajasthan), a private project.
IIPL-Jagdishpur (Uttar Pradesh), a private project.
Brownfield projects reuse existing land, utilities and manpower, so they are faster and cheaper to build.
Investor safeguards:
A Return on Equity band of 12–16%
A foreign exchange rate mitigation mechanism
Old plants waste energy. Nangal uses 6.498 Gcal/MT, against an industry average of 5.95 and a New Energy Norm of 5 Gcal/MT.
Prelims Facts & Static Linkages
Urea demand and supply
Indicator
Figure
Annual consumption
About 400 LMT
Production, 2014–15
225 LMT
Record production, 2023–24
314.07 LMT
Production, 2025–26
293.30 LMT
Reassessed capacity, 2014–15
207.54 LMTPA
Reassessed capacity, 2026–27
269.42 LMTPA
The gap between demand and output is met by imports, which cost foreign exchange.
New Investment Policy (NIP)-2012
It was notified in January 2013 and amended in 2014.
It led to 6 new units of 12.7 LMTPA each, adding 76.2 LMTPA:
Ramagundam (Telangana), run by RFCL
Gorakhpur (UP), Sindri (Jharkhand) and Barauni (Bihar), run by HURL